Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 7)
7.
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
Answer: Option
Explanation:
A's 1 hour's work = | 1 | ; |
4 |
(B + C)'s 1 hour's work = | 1 | ; |
3 |
(A + C)'s 1 hour's work = | 1 | . |
2 |
(A + B + C)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
4 | 3 | 12 |
B's 1 hour's work = | ![]() |
7 | - | 1 | ![]() |
= | 1 | . |
12 | 2 | 12 |
B alone will take 12 hours to do the work.
Discussion:
97 comments Page 7 of 10.
Karthik said:
1 decade ago
A = 1/4.
B&C = 1/3.
A&C = 1/2.
1ST We have to find (A+B+C) therefore (1/4+1/3) = 7/12.
This for total work.
Now we subtract (A&C) value from 7/12.
7/12-1/2=1/12 take reciprocal for that value.
B&C = 1/3.
A&C = 1/2.
1ST We have to find (A+B+C) therefore (1/4+1/3) = 7/12.
This for total work.
Now we subtract (A&C) value from 7/12.
7/12-1/2=1/12 take reciprocal for that value.
Raj said:
1 decade ago
Hi friends, my explanation.
A=1/4.
B and C Compain to work in 3 hours.
so B+C=1/3.
A and C compain to work in 2 hours.
so, A+C=1/2.
Put a=1/4.
1/4+c=1/2.
c=1/4.
B+C=1/3.
1/4+C=1\3.
C=12.
A=1/4.
B and C Compain to work in 3 hours.
so B+C=1/3.
A and C compain to work in 2 hours.
so, A+C=1/2.
Put a=1/4.
1/4+c=1/2.
c=1/4.
B+C=1/3.
1/4+C=1\3.
C=12.
Raj said:
1 decade ago
Hi friends, my explanation.
A=1/4.
B and C Compain to work in 3 hours.
so B+C=1/3.
A and C compain to work in 2 hours.
so, A+C=1/2.
Put a=1/4.
1/4+c=1/2.
c=1/4.
B+C=1/3.
1/4+C=1\3.
C=12.
A=1/4.
B and C Compain to work in 3 hours.
so B+C=1/3.
A and C compain to work in 2 hours.
so, A+C=1/2.
Put a=1/4.
1/4+c=1/2.
c=1/4.
B+C=1/3.
1/4+C=1\3.
C=12.
Paci said:
1 decade ago
How can calculate 7/12 - 1/2 = 1/12?
Yogesh H B said:
1 decade ago
A's 1hr work= 1/4......(1).
B+C=1/3.....(2).
A+C=1/2.......(3).
Solve eqn 1 and 3, we get,
C=1/4.
Put value of C in eqn (2), we get,
B=1/12.
So, B can finish a work in 12 days.
B+C=1/3.....(2).
A+C=1/2.......(3).
Solve eqn 1 and 3, we get,
C=1/4.
Put value of C in eqn (2), we get,
B=1/12.
So, B can finish a work in 12 days.
Elayabharathi said:
1 decade ago
No need of fraction, general understanding.
take lcm for 4,3,2 = 12 parts.
A =3p/d, BC=4p/d AC=6p/d.
so C alone do in (AC-A) 3p/d,
B(BC-C)=1p/d. So for 12 parts it ll take 12 DAYS for B do complete the same work.
question can be twisted like what is the ratio for A:B:C?
what will be the potential for cC?
ABOVE STEPS HAVE ALL THE ANSWERS YOU NEED!
take lcm for 4,3,2 = 12 parts.
A =3p/d, BC=4p/d AC=6p/d.
so C alone do in (AC-A) 3p/d,
B(BC-C)=1p/d. So for 12 parts it ll take 12 DAYS for B do complete the same work.
question can be twisted like what is the ratio for A:B:C?
what will be the potential for cC?
ABOVE STEPS HAVE ALL THE ANSWERS YOU NEED!
Mohit said:
1 decade ago
Why its taken 1/4 and 1/3 ? 4 and 3 why not?
Sai mounika said:
1 decade ago
It is easy to find out.
A+C = 1/2, A = 1/4.
(A+C) - A = 1/4 we got C = 1/4.
We know B+C = 1/3 then substitute C = 1/4 value here then we will get 1/12.
Hence B takes 12 hrs to complete the work.
A+C = 1/2, A = 1/4.
(A+C) - A = 1/4 we got C = 1/4.
We know B+C = 1/3 then substitute C = 1/4 value here then we will get 1/12.
Hence B takes 12 hrs to complete the work.
SIDHARTH said:
1 decade ago
A'S 1 hr work = 1/4.
(B's+ C's) 1hr work = 1/3.
Therefore, (A+B+C's)1 hr work = 1/4+1/3 = 7/12.
Therefore, B's 1hr work = 7/12 - 1/2 = 1/12.
Hence B takes 12 hrs to complete the work.
(B's+ C's) 1hr work = 1/3.
Therefore, (A+B+C's)1 hr work = 1/4+1/3 = 7/12.
Therefore, B's 1hr work = 7/12 - 1/2 = 1/12.
Hence B takes 12 hrs to complete the work.
Kartik said:
1 decade ago
a = 1/4 B+c = 1/3 a+c = 1/2 on subtracting b+c = 1/3 & a+c = 1/2 we got,
b-a = -1/6 and a = 1/4 (given) on putting these value we got b=12 is 1 day work so now total is 12 days.
It's Very Simple.
b-a = -1/6 and a = 1/4 (given) on putting these value we got b=12 is 1 day work so now total is 12 days.
It's Very Simple.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers