Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 7)
7.
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
8 hours
10 hours
12 hours
24 hours
Answer: Option
Explanation:

A's 1 hour's work = 1 ;
4

(B + C)'s 1 hour's work = 1 ;
3

(A + C)'s 1 hour's work = 1 .
2

(A + B + C)'s 1 hour's work = ( 1 + 1 ) = 7 .
4 3 12

B's 1 hour's work = ( 7 - 1 ) = 1 .
12 2 12

Therefore B alone will take 12 hours to do the work.

Discussion:
97 comments Page 7 of 10.

Karthik said:   1 decade ago
A = 1/4.
B&C = 1/3.
A&C = 1/2.

1ST We have to find (A+B+C) therefore (1/4+1/3) = 7/12.

This for total work.
Now we subtract (A&C) value from 7/12.

7/12-1/2=1/12 take reciprocal for that value.

Raj said:   1 decade ago
Hi friends, my explanation.

A=1/4.

B and C Compain to work in 3 hours.
so B+C=1/3.

A and C compain to work in 2 hours.
so, A+C=1/2.

Put a=1/4.
1/4+c=1/2.
c=1/4.

B+C=1/3.
1/4+C=1\3.
C=12.

Raj said:   1 decade ago
Hi friends, my explanation.

A=1/4.

B and C Compain to work in 3 hours.
so B+C=1/3.

A and C compain to work in 2 hours.
so, A+C=1/2.

Put a=1/4.
1/4+c=1/2.
c=1/4.

B+C=1/3.
1/4+C=1\3.
C=12.

Paci said:   1 decade ago
How can calculate 7/12 - 1/2 = 1/12?

Yogesh H B said:   1 decade ago
A's 1hr work= 1/4......(1).
B+C=1/3.....(2).
A+C=1/2.......(3).

Solve eqn 1 and 3, we get,
C=1/4.

Put value of C in eqn (2), we get,
B=1/12.

So, B can finish a work in 12 days.

Elayabharathi said:   1 decade ago
No need of fraction, general understanding.

take lcm for 4,3,2 = 12 parts.

A =3p/d, BC=4p/d AC=6p/d.
so C alone do in (AC-A) 3p/d,

B(BC-C)=1p/d. So for 12 parts it ll take 12 DAYS for B do complete the same work.

question can be twisted like what is the ratio for A:B:C?
what will be the potential for cC?

ABOVE STEPS HAVE ALL THE ANSWERS YOU NEED!

Mohit said:   1 decade ago
Why its taken 1/4 and 1/3 ? 4 and 3 why not?

Sai mounika said:   1 decade ago
It is easy to find out.

A+C = 1/2, A = 1/4.

(A+C) - A = 1/4 we got C = 1/4.

We know B+C = 1/3 then substitute C = 1/4 value here then we will get 1/12.

Hence B takes 12 hrs to complete the work.

SIDHARTH said:   1 decade ago
A'S 1 hr work = 1/4.

(B's+ C's) 1hr work = 1/3.

Therefore, (A+B+C's)1 hr work = 1/4+1/3 = 7/12.

Therefore, B's 1hr work = 7/12 - 1/2 = 1/12.

Hence B takes 12 hrs to complete the work.

Kartik said:   1 decade ago
a = 1/4 B+c = 1/3 a+c = 1/2 on subtracting b+c = 1/3 & a+c = 1/2 we got,

b-a = -1/6 and a = 1/4 (given) on putting these value we got b=12 is 1 day work so now total is 12 days.

It's Very Simple.


Post your comments here:

Your comments will be displayed after verification.