7.
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
8 hours
10 hours
12 hours
24 hours
Answer: Option
Explanation:

A's 1 hour's work = 1 ;
4

(B + C)'s 1 hour's work = 1 ;
3

(A + C)'s 1 hour's work = 1 .
2

(A + B + C)'s 1 hour's work = ( 1 + 1 ) = 7 .
4 3 12

B's 1 hour's work = ( 7 - 1 ) = 1 .
12 2 12

Therefore B alone will take 12 hours to do the work.

Discussion:
100 comments Page 3 of 10.

Xyx said:   9 years ago
How it will 7/12-1/2=1/12?
(1)

Kavit vaishnav said:   1 year ago
A takes 4 hours, 1 hour work = 25%.
For A+C = 2 hours =100% work.
A's part = 50%(for 2 hours),
Remaining part done by C 50% in time 2 hours. So C also does 25% in 1 hour.
Now B+C = 3 Hours = 100% work.
C's part = 3*25% = 75% in 3 hours.
B's part = remaining work = 25% in 3 hours.
So, B' s efficiency = 100% in 12 hours.
(1)

Gayathri said:   3 months ago
A = 1/4
B + C = 1/3 ----> eq(1)
A + C = 1/2 ----> eq(2)
Sub eq(1)-eq(2).
B + C - A - C = 1/3 - 1/2,
B - A = -1/6,
B = -1/6 + 1/4( where A=1/4).
B = 1/12.
Hence B alone takes 12 hours.
(1)

A K BURNWAL said:   3 months ago
A- 4 hours, a's 1 hour = 1/4.
B + C- 3 hours, B + C's 1 hour = 1/3,
A + C- 2 hours, A + C'1 hour = 1/2,
C's 1 hour = 1/2 - 1/4 = 1/4.
B = 1/3 - 1/4 = 1/12.
So, B takes 12 hours to complete work.
(1)

Ashim said:   1 decade ago
4A = 3 (B + C) = 2 (A + C).

4A = 2A + 2C, A = C.

3B + 3C = 2A + 2C.

3B = C.
Or 3B = A.

If A takes 4 hours to complete the work than B takes 12 hours.

Prajwal said:   1 decade ago
A = 1/4.
B + C= 1/3.
A + C= 1/2.
B = ?

C = 1/2 - A.
C = 1/2 - 1/4 = 1/4.
B = 1/3 - C.
B = 1/3 - 1/4.
B = 1/12.

B takes 12 hrs.

Anil said:   1 decade ago
By solving this three equation, we will get the answer.

1/A = 1/4.
1/B + 1/C = 1/3.
1/A + 1/C = 1/2.

Anjum said:   1 decade ago
Thank you everyone for the clear explanation.

Chiru said:   1 decade ago
Thank you everyone for the clear explanation.

Reshma said:   1 decade ago
A = 1/4.
B + C = 1/3.
A + C = 1/2.

Subtract the above 2 equations we get,
B - A = 1/3 - 1/2,
B - A = -1/6,
B = -1/6 + 1/4,
B = 1/12,

So, B takes 12 hours to complete the work.