Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 12)
12.
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
35
40
45
50
Answer: Option
Explanation:

Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.

Then, 4x + 6y = 1 and 3x + 7y = 1 .
8 10

Solving the two equations, we get: x = 11 , y = 1
400 400

1 woman's 1 day's work = 1 .
400

10 women's 1 day's work = 1 x 10 = 1 .
400 40

Hence, 10 women will complete the work in 40 days.

Discussion:
106 comments Page 7 of 11.

MOHAMED SALEEM said:   1 decade ago
Let us sahre CHAN HOW 1 BECOMES 30/8

32x + 48y = 1 --(1) ----> (1) * 30
960x+1440y=30/8 (since 30*32 =960)

Harpreet said:   6 years ago
4 x+6y = 1/8 (I)
3x+7y=1/10.

32x+48y=1....(1)
30x+70y=1....(2)

2x-22y=0
X=11y

4*11y + 6y = 1/8
10y = 1/40.

Muz said:   1 decade ago
Anyone plz tell me, how x in 4x + 6 * 1/400 = 1/8 comes out as "11/400".. i get only "11"

Poonam said:   2 decades ago
Hii,

Can you please explain.

How comes.

4x + 6y = 1/8 and 3x + 7y = 1/10.

X = 11/400, why = 1/400.

Prasant said:   1 decade ago
4x+6y = 1/8
=> 4x+6/400 = 1/8 ...as x=1/400
=> 4x = 1/8-6/400
=> 4x = 11/100
=> x = 11/400

Sasi Lawandi said:   6 years ago
How to get 1 woman's day work = 1/400.

Can you please explain it clearly? Can't understand about it.

ARAVINDHAN said:   1 decade ago
4m+6w=1/8 --(1)

3m+7w=1/10 --(2)

Solve this two we get 10w = 1/40;

So the answer is 40 days.

Srinivas said:   1 decade ago
4x+6y=1/8.

3x+7y=1/10.

Here why you are taking days 1/10 and 1/8?

You mean members=1/days ?

Prasanth said:   9 years ago
4x + 6y = 1/8 and 3x + 7y = 1/10.

How to get x = 11/400 why = 1/400 please explain me.

Priya said:   1 decade ago
Can any one solve this by work equivalence (man days) or by normal equation method?


Post your comments here:

Your comments will be displayed after verification.