Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 12)
12.
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
Answer: Option
Explanation:
Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.
Then, 4x + 6y = | 1 | and 3x + 7y = | 1 | . |
8 | 10 |
Solving the two equations, we get: x = | 11 | , y = | 1 |
400 | 400 |
![]() |
1 | . |
400 |
![]() |
![]() |
1 | x 10 | ![]() |
= | 1 | . |
400 | 40 |
Hence, 10 women will complete the work in 40 days.
Discussion:
106 comments Page 2 of 11.
Mk sai gopala krishna said:
9 years ago
LCM METHOD:
LCM8, 10) = 40 units.
4M + 6W -> 8 days -> 5 units per day.
3M + 7W -> 10days -> 4 units per day.
3 * (4M + 6W) = 5 units per day -----> (1).
4 * (3M + 7W) = 4 units per day -----> (2).
Solving eq (1) and eq (2);
We get 10W =1 unit per day.
Therefore, 40 units/(1 unit per day) = 40 days.
LCM8, 10) = 40 units.
4M + 6W -> 8 days -> 5 units per day.
3M + 7W -> 10days -> 4 units per day.
3 * (4M + 6W) = 5 units per day -----> (1).
4 * (3M + 7W) = 4 units per day -----> (2).
Solving eq (1) and eq (2);
We get 10W =1 unit per day.
Therefore, 40 units/(1 unit per day) = 40 days.
(3)
Dhiru said:
8 years ago
(4m+6w)8 ---> (i)
(3m+7w)10 ---> (ii)
As per question.
(4m+6w)8=(3m+7w)10.
32m+48w=30m+70w.
2m=22w.
m/w=22/2 or 11/1.
Putting m=11 and w= 1 in eq(i)
(4*11+6*1)8 =400.
10 women complete work in 400/10 =40.
(3m+7w)10 ---> (ii)
As per question.
(4m+6w)8=(3m+7w)10.
32m+48w=30m+70w.
2m=22w.
m/w=22/2 or 11/1.
Putting m=11 and w= 1 in eq(i)
(4*11+6*1)8 =400.
10 women complete work in 400/10 =40.
(3)
Vidyadhar said:
4 years ago
For this type of problem, we can use MDH/RW.
M = men, D = days, H = Hours , R = Rupees, W = work.
Note:- In this problem work is done by both men and women.
Total work is same so no need to write in the equation.
The modified formula would look like,
(M + W) x D/W.
(3M + 7W) x 10 = ( 4M x 6W) x 8,
30M + 70W = 32M + 48W,
70W - 48W = 32M - 30M,
22W = 2M.
W/M = 2/22 = 1/11,
i.e women to men efficiency ratio is 1 : 11.
We need to calculate total work,
Total work = efficiency x time.
Total work =( 3x11 + 7x1) x 10 = 400.
Days taken by 10 women to complete the same work is;
400/10x1. Here 1 is the efficiency of women as we calculated earlier.
M = men, D = days, H = Hours , R = Rupees, W = work.
Note:- In this problem work is done by both men and women.
Total work is same so no need to write in the equation.
The modified formula would look like,
(M + W) x D/W.
(3M + 7W) x 10 = ( 4M x 6W) x 8,
30M + 70W = 32M + 48W,
70W - 48W = 32M - 30M,
22W = 2M.
W/M = 2/22 = 1/11,
i.e women to men efficiency ratio is 1 : 11.
We need to calculate total work,
Total work = efficiency x time.
Total work =( 3x11 + 7x1) x 10 = 400.
Days taken by 10 women to complete the same work is;
400/10x1. Here 1 is the efficiency of women as we calculated earlier.
(3)
Ashok Chandane said:
4 years ago
How to solve these two equations?
(3)
Utkarsh said:
7 months ago
@All
Make an equation;
4m + 6w = 8d ---> 1
3m + 7w = 10d ---> 2
Step 2:
Eliminate or make RHS of both the Eqn equal ie:days
32m + 48w = 1d (divide RHS by 8 and multiply LHS by 8)
30m + 70w = 1d (same)
Step3: RHS = LHS( find the relationship of efficient b/w men and women)
32m + 48w = 30m + 70w
2m = 22w
1m = 11w.
Step4: put it in any eqn 1.
44w + 6w = 8d.
50w = 8d.
400w = 1d ..ie to finish the work in 1 day 400 women are needed.
Now to finish the work in 10 days,
400w = x * 10d (x is the amount of work),
x = 400/10 = 40 days.
Make an equation;
4m + 6w = 8d ---> 1
3m + 7w = 10d ---> 2
Step 2:
Eliminate or make RHS of both the Eqn equal ie:days
32m + 48w = 1d (divide RHS by 8 and multiply LHS by 8)
30m + 70w = 1d (same)
Step3: RHS = LHS( find the relationship of efficient b/w men and women)
32m + 48w = 30m + 70w
2m = 22w
1m = 11w.
Step4: put it in any eqn 1.
44w + 6w = 8d.
50w = 8d.
400w = 1d ..ie to finish the work in 1 day 400 women are needed.
Now to finish the work in 10 days,
400w = x * 10d (x is the amount of work),
x = 400/10 = 40 days.
(3)
Arun said:
7 years ago
@All.
(4M+6W)8 = (3M+7W)10
32M+48W = 30M=70M
32M-30M + 48W-70W=0
2M-22W = 0
M = 11W.
Here one Man is equal to 11 Women.
Take 4m+6w to take 8 days equation.
4m=11 * 4w.
4M=44W==> 44W+6W =50.
50 women take 8 days.
10 Women's takes 8 * 5 = 40 days.
(4M+6W)8 = (3M+7W)10
32M+48W = 30M=70M
32M-30M + 48W-70W=0
2M-22W = 0
M = 11W.
Here one Man is equal to 11 Women.
Take 4m+6w to take 8 days equation.
4m=11 * 4w.
4M=44W==> 44W+6W =50.
50 women take 8 days.
10 Women's takes 8 * 5 = 40 days.
(2)
Mohana said:
7 years ago
Hi,
Lets consider men =x , women =y;
Consider equation 1 is 4x+3y=1/8 ;
Consider equation 2 is 3x+7y=1/10;
Before solving above two equation ,
The first equation multiplied by 3,
The second equation multiplied by 4 for cancelling purpose.
After multiplying the equation 1 and 2 becomes,
12x+18y = 3/8.
12x+28y = 4/10.
By solving this above equation by sign change, we get,
-10y= -4/10 + 3/8.
Taking lcm in right and side, it will be;
-10y= (-32+30)/80;
-10y= -2/80:
Therefore y = 2/800 =1/400.
One women work = 1/400;=400 days.
Therefore 10 women work = 10 * 1/400 =1/40 = 40 days.
Thank you.
Lets consider men =x , women =y;
Consider equation 1 is 4x+3y=1/8 ;
Consider equation 2 is 3x+7y=1/10;
Before solving above two equation ,
The first equation multiplied by 3,
The second equation multiplied by 4 for cancelling purpose.
After multiplying the equation 1 and 2 becomes,
12x+18y = 3/8.
12x+28y = 4/10.
By solving this above equation by sign change, we get,
-10y= -4/10 + 3/8.
Taking lcm in right and side, it will be;
-10y= (-32+30)/80;
-10y= -2/80:
Therefore y = 2/800 =1/400.
One women work = 1/400;=400 days.
Therefore 10 women work = 10 * 1/400 =1/40 = 40 days.
Thank you.
(1)
Kishor said:
2 decades ago
If 4 men and 6 women can complete a work in 8 days
4 men and 1 women can complete a work in=6* 8 days
1 men and 1 women can complete a work in=4*6* 8 days
1 men and 7 women can complete a work in=4*6*8/7 days
3 men and 7 women can complete a work in=4*6*8/(3*7) days
=64/7days
which is not 10 days as given in the question
4 men and 1 women can complete a work in=6* 8 days
1 men and 1 women can complete a work in=4*6* 8 days
1 men and 7 women can complete a work in=4*6*8/7 days
3 men and 7 women can complete a work in=4*6*8/(3*7) days
=64/7days
which is not 10 days as given in the question
Shehina said:
2 decades ago
How 1/40 become 40?
Nagu said:
2 decades ago
Hi Kishor,
you are wrong. This question is correct and the explanation is also correct.
Please refer once again.
you are wrong. This question is correct and the explanation is also correct.
Please refer once again.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers