Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 16)
16.
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
6 days
10 days
15 days
20 days
Answer: Option
Explanation:

Work done by X in 4 days = 1 x 4 = 1 .
20 5

Remaining work = 1 - 1 = 4 .
5 5

(X + Y)'s 1 day's work = 1 + 1 = 8 = 2 .
20 12 60 15

Now, 2 work is done by X and Y in 1 day.
15

So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5

Hence, total time taken = (6 + 4) days = 10 days.

Discussion:
68 comments Page 6 of 7.

Nikhil said:   2 decades ago
2/15 work done by x and y in one day.

Then how you are taking reciprocal 15/2*4/5.

Nagu said:   2 decades ago
2/15 is work is done by X and Y in 1 day.
And 4/5 is Remaining work


suppose X and Y together take A days to complete the remaining wotk then

A*2/15 = 4/5

now A = 4/5 * 15/2

so A = 6 days

i think you understood the logic behind that

Anusha said:   1 decade ago
a = b+b (0.3).

(1/23) = 1.3 b.

b = (10/{23*13}).

b = (10/299).

a+b = 1/13.

So 13 days.

Mahesh said:   1 decade ago
1day per x work as = 1/20 && y= 1/12..

x do work 4days ..then 4*1/20=1/5 then remaining work= 1-1/5=4/5

Remaining work's done by y i.e. 1work ---> 12
4/5 ------> x
x=4/5 * 12 = 48/5 = 9.6day nearly = 10days..

It's good method to understand GUYS..!

Shro said:   1 decade ago
6+4 =10
Is here 4 takes from the question? " X started the work alone and then after 4 days"

ANURAG said:   1 decade ago
(x and y)'s one day work= 2/15
Therefore total number of days for the total work= 15/2
And,total number of days for 4/5 of the work=( 15/2 )*(4/5)
Hence total time = 6+4 = 10 days

Ashish said:   1 decade ago
Work done by A in 1 day=1/20.
Work done by B in 1 day=1/12.
(A+B) 'S 1 DAY WORK=1/20+1/12=8/60.
So A can work in 4 days =4*1/20=1/5.
So remaining work=1-1/5=4/5.
So 4/5 of work done by (A+B) =4/5*60/8.
=6 DAYS.
TOTAL DAY TAKEN WILL BE=6+4=10 DAYS.

Padma said:   1 decade ago
A+B can work
1/20+1/12=8/60.

A can work =4*1/20=1/5.

Remaining work=1-1/5=4/5.

A+B work to days 1/n formula=60/8.

60/8*4/5=6 days.

Total day taken will be=6+4=10.

Zia said:   1 decade ago
Hi, I have a shortcut.

(X-a)*Y/X+Y [X=20,Y=12,a=4]

= (20-4)*12/20+12.

= 16*12/32.

= 12/2.

= 6.

So, total time taken (6+4) = 10 days.

Amarnath said:   1 decade ago
Sorry @Zia Don't apply formulas it loses confidence for others. Whatever they know will apply if try tell in simple answer don't tell with formulas.


Post your comments here:

Your comments will be displayed after verification.