Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 16)
16.
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
Answer: Option
Explanation:
Work done by X in 4 days = | ![]() |
1 | x 4 | ![]() |
= | 1 | . |
20 | 5 |
Remaining work = | ![]() |
1 - | 1 | ![]() |
= | 4 | . |
5 | 5 |
(X + Y)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 8 | = | 2 | . |
20 | 12 | 60 | 15 |
Now, | 2 | work is done by X and Y in 1 day. |
15 |
So, | 4 | work will be done by X and Y in | ![]() |
15 | x | 4 | ![]() |
= 6 days. |
5 | 2 | 5 |
Hence, total time taken = (6 + 4) days = 10 days.
Discussion:
68 comments Page 2 of 7.
Lydia said:
1 decade ago
Please explain the remaining work.
Srikanth Chowdary said:
1 decade ago
Mitra please explain clearly.
Zeeshan said:
1 decade ago
Well done harsha.
Anwesh said:
1 decade ago
Harsha realy well done.
Sahib said:
1 decade ago
Take it this way
1/5 work x does in 4 days
Remaining 4/5 is to be found
X+y does 1/20+1/12 in 1 day
Therefore x+y=2/15 w/d
Therefore 4/5 w = 2/15(w/d)/4/5(w)
We get 1/6(1/d)
Therefore 6 days
Therefore total wrk in 10 days
1/5 work x does in 4 days
Remaining 4/5 is to be found
X+y does 1/20+1/12 in 1 day
Therefore x+y=2/15 w/d
Therefore 4/5 w = 2/15(w/d)/4/5(w)
We get 1/6(1/d)
Therefore 6 days
Therefore total wrk in 10 days
Sree said:
1 decade ago
How 6+4?y should we add. Please help.
Santosh said:
1 decade ago
Well a simple logic
1day work x =1/20
y=1/12
x first start and works upto 4 days=4*1/20
then both x and y works upto some day to completework=a(1/20+1/12)
add (4*1/20)+a(1/20+1/12)=1
we will get the days where both x and y worked=a=6
So total days to complete work =4+6=10.
1day work x =1/20
y=1/12
x first start and works upto 4 days=4*1/20
then both x and y works upto some day to completework=a(1/20+1/12)
add (4*1/20)+a(1/20+1/12)=1
we will get the days where both x and y worked=a=6
So total days to complete work =4+6=10.
Swetha said:
1 decade ago
x can do a work in 20 days
y can do a work in 12 days
To find total work ,take LCM of 20 and 12 i.e 60
Therefore Total work =60
x's 1 day capacity =60/20 =3
Y's 1 day capacity =60/12 =5
Since x alone did work for 4 days,
4*3=12 ,
12 work done in 4 days
there fore remaining work = 60-12 =48
Remaining work was completed by both
remaining work / (x's per day capacity +y's per day capacity)=48/6= 6
therefore remaining work was completed in 6 days
Total work was completed in 4 + 6 = 10 days.
I hope this is useful...
y can do a work in 12 days
To find total work ,take LCM of 20 and 12 i.e 60
Therefore Total work =60
x's 1 day capacity =60/20 =3
Y's 1 day capacity =60/12 =5
Since x alone did work for 4 days,
4*3=12 ,
12 work done in 4 days
there fore remaining work = 60-12 =48
Remaining work was completed by both
remaining work / (x's per day capacity +y's per day capacity)=48/6= 6
therefore remaining work was completed in 6 days
Total work was completed in 4 + 6 = 10 days.
I hope this is useful...
Mahesh said:
1 decade ago
1day per x work as = 1/20 && y= 1/12..
x do work 4days ..then 4*1/20=1/5 then remaining work= 1-1/5=4/5
Remaining work's done by y i.e. 1work ---> 12
4/5 ------> x
x=4/5 * 12 = 48/5 = 9.6day nearly = 10days..
It's good method to understand GUYS..!
x do work 4days ..then 4*1/20=1/5 then remaining work= 1-1/5=4/5
Remaining work's done by y i.e. 1work ---> 12
4/5 ------> x
x=4/5 * 12 = 48/5 = 9.6day nearly = 10days..
It's good method to understand GUYS..!
Shro said:
1 decade ago
6+4 =10
Is here 4 takes from the question? " X started the work alone and then after 4 days"
Is here 4 takes from the question? " X started the work alone and then after 4 days"
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers