20.
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
15
16
18
25
Answer: Option
Explanation:

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.

Suppose Tanya takes x days to do the work.

5 : 4 :: 20 : x    x = 4 x 20
5

x = 16 days.

Hence, Tanya takes 16 days to complete the work.

Discussion:
94 comments Page 5 of 10.

Jitendra said:   1 decade ago
Why we should consider 125 and 100.

If we consider that Sakshi 100 and Tanya 75 then,

100 : 75 :: 20 : x.

= 100/75 = 20/x.

=> x = 15 days.

Sanjoy said:   1 decade ago
100T = 125S, 20S = 1, consider x day required for Tania.

4T = 5S, S = 1/20, Tx =1.
4T = 5*1/20 1/16x = 1.

4T = 1/4 x = 16.
T = 1/16.

So Tania required 16days to complete the work.

Vijayalakshmi R said:   1 decade ago
S can do a work in 20 days so, s=1/20;

T can do a work 25% more efficient than S.

So, T = 1/20 + (25/100*1/20).

Finally we got T = 1/16.

So 16 is the correct answer.

I am sure about my answer so don't confuse, it may be 25 or other else.

Vamsi said:   1 decade ago
If Tanya is 25% more efficient than Sakshi, then as 25% of 20 is 5. Tanya should complete the work in 15 days not 16 days.

Devi prasad said:   10 years ago
Their is mixed view of this question but we got both the answer correctly.

Raghu said:   10 years ago
The answer is 15 let me tell you.

Tanya is 25% efficient than Sakshi.

If Sakshi do a work in 24 hours then Tanya will do in 18 hours because 12 is 50% of 24. 6 is 25% of 24.

So Tanya take 6 hours less time than Sakshi, so reduce 6 hours in every day upto 20 days 6 x 20 = 120 i.e 5 days.

20 days - 5 days = 15 days.

Sonu jangra said:   10 years ago
Sakshi do 1 day's the work = 1/20.

Now, Tanya do the work 25% more efficient than Sakshi = 1/20*25/100 = 1/80.

So, Tanya will do the total work = 1/20+1/80 = 5/80 = 1/16.

So 1*16/1 = 16 days.

Pankaj said:   10 years ago
Answer will be 25.

If the ratio taken is T:S::T:S.

125:100::X:20.

5:4::X:20 = 25.

x is no. of days taken by Tanya complete a work.

Subhasis said:   10 years ago
What if I think tanaya takes 75 days and sakshi takes 100 days, then answer will be 15 days.

Suresh KS said:   9 years ago
Hi friends I agree your answer is 16 based on your methods.

So please let me know how many days Tanya takes if she is 50% more efficient than sakshi based on your methods.