Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
Answer: Option
Explanation:
Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.
Suppose Tanya takes x days to do the work.
5 : 4 :: 20 : x ![]() |
![]() |
4 x 20 | ![]() |
5 |
x = 16 days.
Hence, Tanya takes 16 days to complete the work.
Discussion:
94 comments Page 5 of 10.
Jitendra said:
1 decade ago
Why we should consider 125 and 100.
If we consider that Sakshi 100 and Tanya 75 then,
100 : 75 :: 20 : x.
= 100/75 = 20/x.
=> x = 15 days.
If we consider that Sakshi 100 and Tanya 75 then,
100 : 75 :: 20 : x.
= 100/75 = 20/x.
=> x = 15 days.
Sanjoy said:
1 decade ago
100T = 125S, 20S = 1, consider x day required for Tania.
4T = 5S, S = 1/20, Tx =1.
4T = 5*1/20 1/16x = 1.
4T = 1/4 x = 16.
T = 1/16.
So Tania required 16days to complete the work.
4T = 5S, S = 1/20, Tx =1.
4T = 5*1/20 1/16x = 1.
4T = 1/4 x = 16.
T = 1/16.
So Tania required 16days to complete the work.
Vijayalakshmi R said:
1 decade ago
S can do a work in 20 days so, s=1/20;
T can do a work 25% more efficient than S.
So, T = 1/20 + (25/100*1/20).
Finally we got T = 1/16.
So 16 is the correct answer.
I am sure about my answer so don't confuse, it may be 25 or other else.
T can do a work 25% more efficient than S.
So, T = 1/20 + (25/100*1/20).
Finally we got T = 1/16.
So 16 is the correct answer.
I am sure about my answer so don't confuse, it may be 25 or other else.
Vamsi said:
1 decade ago
If Tanya is 25% more efficient than Sakshi, then as 25% of 20 is 5. Tanya should complete the work in 15 days not 16 days.
Devi prasad said:
10 years ago
Their is mixed view of this question but we got both the answer correctly.
Raghu said:
10 years ago
The answer is 15 let me tell you.
Tanya is 25% efficient than Sakshi.
If Sakshi do a work in 24 hours then Tanya will do in 18 hours because 12 is 50% of 24. 6 is 25% of 24.
So Tanya take 6 hours less time than Sakshi, so reduce 6 hours in every day upto 20 days 6 x 20 = 120 i.e 5 days.
20 days - 5 days = 15 days.
Tanya is 25% efficient than Sakshi.
If Sakshi do a work in 24 hours then Tanya will do in 18 hours because 12 is 50% of 24. 6 is 25% of 24.
So Tanya take 6 hours less time than Sakshi, so reduce 6 hours in every day upto 20 days 6 x 20 = 120 i.e 5 days.
20 days - 5 days = 15 days.
Sonu jangra said:
10 years ago
Sakshi do 1 day's the work = 1/20.
Now, Tanya do the work 25% more efficient than Sakshi = 1/20*25/100 = 1/80.
So, Tanya will do the total work = 1/20+1/80 = 5/80 = 1/16.
So 1*16/1 = 16 days.
Now, Tanya do the work 25% more efficient than Sakshi = 1/20*25/100 = 1/80.
So, Tanya will do the total work = 1/20+1/80 = 5/80 = 1/16.
So 1*16/1 = 16 days.
Pankaj said:
10 years ago
Answer will be 25.
If the ratio taken is T:S::T:S.
125:100::X:20.
5:4::X:20 = 25.
x is no. of days taken by Tanya complete a work.
If the ratio taken is T:S::T:S.
125:100::X:20.
5:4::X:20 = 25.
x is no. of days taken by Tanya complete a work.
Subhasis said:
10 years ago
What if I think tanaya takes 75 days and sakshi takes 100 days, then answer will be 15 days.
Suresh KS said:
9 years ago
Hi friends I agree your answer is 16 based on your methods.
So please let me know how many days Tanya takes if she is 50% more efficient than sakshi based on your methods.
So please let me know how many days Tanya takes if she is 50% more efficient than sakshi based on your methods.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers