Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 8)
8.
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
Answer: Option
Explanation:
(A + B)'s 1 day's work = | 1 |
10 |
C's 1 day's work = | 1 |
50 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 6 | = | 3 | . .... (i) |
10 | 50 | 50 | 25 |
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
From (i) and (ii), we get: 2 x (A's 1 day's work) = | 3 |
25 |
![]() |
3 | . |
50 |
![]() |
![]() |
1 | - | 3 | ![]() |
= | 2 | = | 1 | . |
10 | 50 | 50 | 25 |
So, B alone could do the work in 25 days.
Discussion:
146 comments Page 2 of 15.
Dhivyasree said:
3 years ago
Here, 1 day's work of a and b is(50/10) = 5.
1 day work of c is(50/50) = 1
a+b+c=(5+1)=>6->(1).
Given that a's time=sum of b's and c's time so,a=b+c
we can write a=b+c as b=a-c and then substitute this in (1)
that is a+b+c=6.
a+a-c+c=6=>2a=6->a=3.
Then later in that (1).
a+b+c = 6.
b = 6 - a - c,
b = 6 - 3 - 1,
b = 2.
That is 50/2=>25days.
1 day work of c is(50/50) = 1
a+b+c=(5+1)=>6->(1).
Given that a's time=sum of b's and c's time so,a=b+c
we can write a=b+c as b=a-c and then substitute this in (1)
that is a+b+c=6.
a+a-c+c=6=>2a=6->a=3.
Then later in that (1).
a+b+c = 6.
b = 6 - a - c,
b = 6 - 3 - 1,
b = 2.
That is 50/2=>25days.
(21)
Dewesh Kumar said:
3 years ago
A = B+C ,
A - C = B ---> (i).
Then,
A + B + C = 1/10 + 150 = 3/25.
From (i) putting a value of B
A+B+C= 3/25,
A+A - C + C = 3/25.
2A = 3/25.
A = 3/50.
Now, A+B = 1/10,
Putting A = 3/50,
B = 1/10-3/50.
B = 1/25 (B one day work) then total days is 25.
A - C = B ---> (i).
Then,
A + B + C = 1/10 + 150 = 3/25.
From (i) putting a value of B
A+B+C= 3/25,
A+A - C + C = 3/25.
2A = 3/25.
A = 3/50.
Now, A+B = 1/10,
Putting A = 3/50,
B = 1/10-3/50.
B = 1/25 (B one day work) then total days is 25.
(110)
Shubham Uttam Bandgar said:
3 years ago
If A = B+C.
So A-B =C.
i,e A-B = 1/50 ----> eq 1
And
A+B = 1/10 ----> eq 2.
From eq 2 - eq 1 we will get the answer.
.
So A-B =C.
i,e A-B = 1/50 ----> eq 1
And
A+B = 1/10 ----> eq 2.
From eq 2 - eq 1 we will get the answer.
.
(24)
Neeraj said:
4 years ago
Great, Thanks everyone for explaining.
(13)
Gaurabbc said:
4 years ago
Time taken by A and B =10 days and Time taken by C =50 days
Total work=50 units
Efficiency of A and B = 5
The efficiency of C =1
A=B+C is given
A+B=5 => B+C+B=5 => 2B+C=5
2B+1=5 =>2B=4
B=2 is the efficiency
Time taken by B= work /efficiency of B =>50/2 =25.
Therefore, B can complete the work in 25days.
Total work=50 units
Efficiency of A and B = 5
The efficiency of C =1
A=B+C is given
A+B=5 => B+C+B=5 => 2B+C=5
2B+1=5 =>2B=4
B=2 is the efficiency
Time taken by B= work /efficiency of B =>50/2 =25.
Therefore, B can complete the work in 25days.
(45)
Siddhant patel said:
4 years ago
A+B can finish work in 10 days so its efficiency is 5 unit per day.
c can finish work in 50 days so its efficiency will be 1 unit per day.
So from here, we can calculate the total work, which will be 50 unit.
now according to the question,
Efficiency of A =efficiency of B+C
Adding B both sides,
A+B=2B+C
5=2B+1.
Therefore the efficiency of B will be,2 unit per day.
Now since the total work is 50 unit,we can calculate the time,
Time = total work/efficiency
Time=25 days.
c can finish work in 50 days so its efficiency will be 1 unit per day.
So from here, we can calculate the total work, which will be 50 unit.
now according to the question,
Efficiency of A =efficiency of B+C
Adding B both sides,
A+B=2B+C
5=2B+1.
Therefore the efficiency of B will be,2 unit per day.
Now since the total work is 50 unit,we can calculate the time,
Time = total work/efficiency
Time=25 days.
(7)
Aswathi Radhakrishnan said:
4 years ago
Total work is = 50
C's efficiency = 50/50=1.
A+B's Efficiency = 50/10=5.
A+B+C's Efficiency = 5 + 1 = 6.
A = B+C,
B+C+B+C=6,
2(B+C)=6,
B+C= 6/2 =3,
A's Efficiency = 3,
So B's Efficiency =5-3 =2.
Hence B alone do it in 50/2 = 25 Days.
C's efficiency = 50/50=1.
A+B's Efficiency = 50/10=5.
A+B+C's Efficiency = 5 + 1 = 6.
A = B+C,
B+C+B+C=6,
2(B+C)=6,
B+C= 6/2 =3,
A's Efficiency = 3,
So B's Efficiency =5-3 =2.
Hence B alone do it in 50/2 = 25 Days.
(11)
Tushar said:
4 years ago
1/A+1/B=1/10 ---> EQN1.
Given that,
1/C = 1/50,
1/A=1/B+1/C ---> EQN2.
From EQN1 and EQN2 we get,
1/B + 1/B+1/C = 1/10,
2/B + 1/C = 1/10,
2/B + 1/50 = 1/10,
2/B = 2/25,
1/B = 1/25.
Hence B alone can do it in 25 Days.
Given that,
1/C = 1/50,
1/A=1/B+1/C ---> EQN2.
From EQN1 and EQN2 we get,
1/B + 1/B+1/C = 1/10,
2/B + 1/C = 1/10,
2/B + 1/50 = 1/10,
2/B = 2/25,
1/B = 1/25.
Hence B alone can do it in 25 Days.
(4)
Bunny said:
4 years ago
They gave A = B+C, A+B = 10Days, C=50 Days;
A+B = 1/10;
since A = B+C;
B+C+B = 1/10;
2B+C = 1/10;
2B+1/50 = 1/10;
therefore B = 1/25;
B can complete in 25 days.
A+B = 1/10;
since A = B+C;
B+C+B = 1/10;
2B+C = 1/10;
2B+1/50 = 1/10;
therefore B = 1/25;
B can complete in 25 days.
(14)
Stevan said:
4 years ago
A = B + C,
A+B = 10 or A and B's one day work A+B=1/10.
C=50 or C=1/50.
A+B=1/10 (Since A=B+C),
B+C+B=1/10,
2B+1/50=1/10,
2B=1/10-1/50,
2B=2/25,
B=2/25*1/2.
B=1/25 (Which is one day's work).
B would take 25 days to complete certain work.
A+B = 10 or A and B's one day work A+B=1/10.
C=50 or C=1/50.
A+B=1/10 (Since A=B+C),
B+C+B=1/10,
2B+1/50=1/10,
2B=1/10-1/50,
2B=2/25,
B=2/25*1/2.
B=1/25 (Which is one day's work).
B would take 25 days to complete certain work.
(3)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers