8.
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
Answer: Option
Explanation:
(A + B)'s 1 day's work = | 1 |
10 |
C's 1 day's work = | 1 |
50 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 6 | = | 3 | . .... (i) |
10 | 50 | 50 | 25 |
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
From (i) and (ii), we get: 2 x (A's 1 day's work) = | 3 |
25 |
![]() |
3 | . |
50 |
![]() |
![]() |
1 | - | 3 | ![]() |
= | 2 | = | 1 | . |
10 | 50 | 50 | 25 |
So, B alone could do the work in 25 days.
Discussion:
146 comments Page 13 of 15.
Nikhil said:
1 decade ago
Mr.Awoke your method is awesome and moreover its applicable to all such type of probs...thanks!
Mohanapriyadarshini said:
1 decade ago
@awoke
How come 2 b's ?
A + B = 1/10 but A = B + C, then
A + B = B + B + C = 1/10 and C = 1/50
a value is a+b ,what about b+c, why you are adding b+b+c ?
How come 2 b's ?
A + B = 1/10 but A = B + C, then
A + B = B + B + C = 1/10 and C = 1/50
a value is a+b ,what about b+c, why you are adding b+b+c ?
Suresh said:
1 decade ago
From given statement
A+B+C = 6/50 ( A+B = 1/10 and C = 1/50)
Substitute A= B+C in above equation to get A= 3/50
3/50+B+1/50 = 6/50
B = 1/25
25 days
A+B+C = 6/50 ( A+B = 1/10 and C = 1/50)
Substitute A= B+C in above equation to get A= 3/50
3/50+B+1/50 = 6/50
B = 1/25
25 days
DHARMENDRA said:
1 decade ago
A=B+C-----------------(1)
A+B=1/10--------------(2)
C=1/50----------------(3)
(1)+(2)
(B+C)+B=1/10-----------(4)
(3)+(4)
B+(1/50)+B=1/10
2B=(1/10)-(1/50)
B=1/25
SO B COMPLETE THE TASK IN 25 DAYS
A+B=1/10--------------(2)
C=1/50----------------(3)
(1)+(2)
(B+C)+B=1/10-----------(4)
(3)+(4)
B+(1/50)+B=1/10
2B=(1/10)-(1/50)
B=1/25
SO B COMPLETE THE TASK IN 25 DAYS
Nagu said:
1 decade ago
Hi Guys, sorry for the late and here is the explanation about you doubt.
In my previous explanation I mentioned
(a+b+c)'s one day work = 3/25
and a+b+c = 2a here b+c=a means a's one day work = b+c's one day work
then a's one day work+(b+c)'s one day work = 3/25
so a+a = 3/25
2a = 3/25
so here 2* a's one days work = 3/25
So I think u can under stand now
keep practicing.....
In my previous explanation I mentioned
(a+b+c)'s one day work = 3/25
and a+b+c = 2a here b+c=a means a's one day work = b+c's one day work
then a's one day work+(b+c)'s one day work = 3/25
so a+a = 3/25
2a = 3/25
so here 2* a's one days work = 3/25
So I think u can under stand now
keep practicing.....
Anchal said:
1 decade ago
Best method is Awoke method, because this is shortcut for doing in competative exams. But for understandin the solution, we can see Nagu's method.
So good job have done by both the guys. Thankyou.
So good job have done by both the guys. Thankyou.
Pratiksha said:
1 decade ago
Thanku sneha I getting your explanation.
Logunath said:
1 decade ago
We have....
A+B=1/10......(2)
A=B+C,
C=1/50,
We can set,
A-B=C
A-B=1/50......(1)
solving 1 and 2...
A=3/50,
so B=1/25,
B can do it in 25 day's.
A+B=1/10......(2)
A=B+C,
C=1/50,
We can set,
A-B=C
A-B=1/50......(1)
solving 1 and 2...
A=3/50,
so B=1/25,
B can do it in 25 day's.
Rajni Saini said:
1 decade ago
Awoke u r grreaatt dear.thnx a lot.
Sumedha said:
1 decade ago
@Awoke.
Your short cut method is great.
Your short cut method is great.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers