Aptitude - Chain Rule - Discussion

Discussion Forum : Chain Rule - General Questions (Q.No. 1)
1.
3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?
9
10
11
12
Answer: Option
Explanation:

Let the required number of working hours per day be x.

More pumps, Less working hours per day (Indirect Proportion)

Less days, More working hours per day (Indirect Proportion)

Pumps 4 : 3 :: 8 : x
Days 1 : 2

4 x 1 x x = 3 x 2 x 8

x = (3 x 2 x 8)
(4)

x = 12.

Discussion:
69 comments Page 2 of 7.

Celita Lewis said:   1 decade ago
If 3 pumps work for 8 hours than total hours in 1 day is 3 * 8 = 24 hours.

So in 2 days total hours of work is 48 hours.

So for 4 pumps the work distributed is (48 / 4) = 12 hours.

Math Master said:   1 decade ago
Better you do like this:
3 pumps take 16 hrs total (8 Hrs a day)
If 1 pump will be working then, it will need 16*3=48 hrs
1 pump need 48 Hrs
If I contribute 4 pumps then
48/4=12 hrs.

Shivam Mehta said:   6 years ago
There is a direct formula m1d1t1w2= m2d2t2w1,
where m1,m2 = no of men case 1,2.
w1,w2= work done in case 1,2.
d1,d2= no of days in case 1,2.
t1,t2= no of hours in case 1,2.
(7)

Sanskriti said:   8 years ago
Working 8 hours a day, 12 people can do a piece of work in 15 days. How many people will complete the same work in 16 days working 9 hours a day?

Please solve the problem.

Suhani said:   8 years ago
8 hours * 12 people * 15 days = work;
Let, x people will complete the work in 16 days so-
9 hours * x people * 16 days = work,
8 * 12 * 15 = 9 * x * 16,
x = 10 people.

Deepika said:   1 decade ago
Hey I have one simple way that is ma formula is n*D*H/w = N1*D1*H1/W1.

Where n = no.of men.
d = days.
h = hours.
w = work.

So my opinion is 3*8*2 = 4*1*x.

x = 12.

Aara said:   1 decade ago
Why this formula given below does not work with this question but works with other such similar questions?

(Machine (1) x Time) /Work = (Machine (2) x Time) /Work.

Isiko Abudallah said:   6 years ago
Let x be the number of hours taken by the second pump.
A : B
Pump 3 : 4
Days 2 : 1
Hours 8 : x

Hour taken by B,
3*2*8 = 4*1*x.
48 = 4x.
x = 12.
(48)

Sandeep said:   1 decade ago
GIVEN: 3 pumps' 1 hour's work= 1/16
SOLUTION : 1 pump's 1 hour's work= 1/48
4 pumps' 1 hour's work= (1/48)*4 = 1/12
hence 4 pumps will finish the work in 12 hours

Ashish and Amartya said:   1 decade ago
We found a new method.
step 1- calc the total time for 3 pumps ie(2*8)
2- now for 1 pump time=(2*8)*3
3- " " 4 pump time = ((2*8)*3)/4..ans.


Post your comments here:

Your comments will be displayed after verification.