Civil Engineering - Engineering Economy

Why Civil Engineering Engineering Economy?

In this section you can learn and practice Civil Engineering Questions based on "Engineering Economy" and improve your skills in order to face the interview, competitive examination and various entrance test (CAT, GATE, GRE, MAT, Bank Exam, Railway Exam etc.) with full confidence.

Where can I get Civil Engineering Engineering Economy questions and answers with explanation?

IndiaBIX provides you lots of fully solved Civil Engineering (Engineering Economy) questions and answers with Explanation. Solved examples with detailed answer description, explanation are given and it would be easy to understand. All students, freshers can download Civil Engineering Engineering Economy quiz questions with answers as PDF files and eBooks.

Where can I get Civil Engineering Engineering Economy Interview Questions and Answers (objective type, multiple choice)?

Here you can find objective type Civil Engineering Engineering Economy questions and answers for interview and entrance examination. Multiple choice and true or false type questions are also provided.

How to solve Civil Engineering Engineering Economy problems?

You can easily solve all kind of Civil Engineering questions based on Engineering Economy by practicing the objective type exercises given below, also get shortcut methods to solve Civil Engineering Engineering Economy problems.

Exercise :: Engineering Economy - Section 1

1. 

Which one of the following questions is relevant to the construction estimates :

A. Did the estimators precisely evaluate site conditions ?
B. Did the estimators use short cut methods which may be un realistic in their situation ?
C. How much money will the contractor's risk, loosing if he Were to submit bid on the raw estimate of cost.
D. All of these

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

2. 

The ratio obtained by dividing 'quick assests' by current liabilities is called

A. Turnover ratio
B. Acid test ratio
C. Solvency ratio
D. None of these.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

3. 

Which one of the following definitions, is correct ?

A. The ratio of total debt to share holder's equity is called 'debt ratio'.
B. The ratio debt-to-total assests is called Debt-to-total assest ratio.
C. The ratio of earnings before interest and taxes for a particular reporting period to the amount of interest charges for the period, is called interest coverage ratio.
D. All of these

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

4. 

Pick up the element of the cost from the following:

A. direct material
B. direct labour
C. Over head
D. All of these

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

5. 

The estimator for definitive estimates must be able :

A. and an all-around construction expert.
B. to read the plans and specifications to determine accurate quantities of permanent materials and installed Equipment.
C. to express the job material requirements in dimensions suitable for costing and construction supplies.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.